Work on buildings Z5 and Z4 is well advanced – in Z5, masonry work, window installation, and most of the facade and insulation work have been completed, while in Z4, partition walls and window installation have been completed, and insulation and roofing have begun.
The investment is at an advanced stage – construction and masonry work is underway in buildings B and C, joinery is being installed, the foundations in building A are being concreted, and the excavation has been secured.
Insulation layers have been completed, soffits and canopies have been covered. The flashings have been completed and the external parapets have been fixed.